Pyramid Grand Vista Sector 73
Pyramid Grand Vista Sector 73
|
Sr.No |
Work Description |
Progress |
|
|
1 |
Main Entrance Gate Work |
0% |
|
|
2 |
Laying Services Work |
0% |
|
|
3 |
Rainwater Harvesting Work |
0% |
|
|
4 |
STP Structure Work |
0% |
|
|
5 |
UGT Structure Work |
0% |
|
|
6 |
ESS Structure Work |
0% |
|
|
7 |
Road Work |
10% |
|
|
8 |
Hardscape (street light, signage, etc) Work |
5% |
|
|
9 |
Softscape (Gardens, tree plantation, scrub plantation, etc) Work |
25% |