Pyramid Urban Sector – 67A as on 22 February, 2021.

Discover more

← Back to Construction Updates

Pyramid Urban Sector - 67A

Pyramid Urban Sector - 67A

Sr.No

Towers

Work Description

Progress 

1

1,2,3,4,5,6,7,8,9,10,11,12

Structure Works 

100%

2

 Commercial Block

Structure 

80%

3

10,11,12

Finishing Work 

70%

4

9

Finishing Work 

55%

5

7,8

Finishing Work 

30%

6

6

Finishing Work 

50%

7

5

Finishing Work  

70%

8

3,4

Finishing Work  

30%

9

2

Finishing Work  

12%

10

1

Finishing Work  

15%

11

 1,2,3,4,5,6,7,8,9,10,11,12

External Development

35%