Emerald Estate, Rewari as on 15 June, 2026.

Discover more

← Back to Construction Updates

Emerald Estate, Rewari

Emerald Estate, Rewari

Sr.No

 

Work Description

Progress 

1

 

Main Entrance Gate Work

85%

2

 

Sewer Line Work 

95%

3

 

Storm Water Work

90%

4

 

Rainwater Harvesting Work 

90%

5

 

Sewarage Treatment Plant Work 

75%

6

 

Under Ground Water Tank Work 

75%

7

 

Water Supply Work 

70%

8

 

Road Work 

75%

9

 

Green Area & Plantation Along Boundary Wall Work 

75%

10

 

Meter Room & ESS Work

100%

11

 

External Boundary Wall Work 

95%

12

 

External Developments, Street Lights, Landscaping Work 

75%

13

 

Guard Room Work 

95%