Pyramid Elite Sector-86 as on 06 October, 2023.

Discover more

← Back to Construction Updates

Pyramid Elite Sector-86

Pyramid Elite Sector-86

Sr.No

Towers

Work Description

Progress 

1

1,2,3,4,5,6,7, UGT, STP, ESS, VCB ROOM, COMMERCIAL, METER ROOM & VCB ROOM

Sub Structure Work

100%

2

1,2,3,4,5,6,7, UGT, STP, ESS, VCB ROOM 

Super Structure Work

100%

3

COMMERCIAL

Super Structure Work 

95%

4

1

Finishing Work 

85% (Tile fixing 100% complete
putty work in progress)

5

2

Finishing Work 

90%

6

3

Finishing Work 

90%

7

4

Finishing Work 

90%

8

5

Finishing Work 

90%

9

6

Finishing Work 

95%

10

7

Finishing Work 

95%

11

STP

Finishing Work 

100%

12

UGT

Finishing Work 

100%

13

COMMERCIAL 

Finishing Work  

30%

14

VCB ROOM

Finishing Work 

75%

15

ESS

Finishing Work  

75%

Go to Updates