Work Description

Progress 

1

Main Entrance Gate

100%

2

 Sewer Line Work

85%

3

Storm Water Work

75%

4

Rain water Harvesting

20%

5

Sewarage Treatment Plant Work

25%

6

Under Ground Water Tank Work

20%

7

Water Supply Work

30%

8

Road Work

10%

9

Electrical Sub-station

5%

10

Fire Fighting Services

30%

11

 Laying of Cables

5%

12

External Developments, Street Lights, Landscaping

10%